Week 1: Preparation & Demolition
- ✔ Site inspection & layout planning
- ✔ Demolition of existing kitchen
- ✔ Removal of cabinetry, appliances & flooring
- ✔ Structural changes (if required)
End of Week 1: Electrical & Plumbing Rough-In
- ✔ Electricians install wiring & lighting points
- ✔ Plumbing rough-in (sink, dishwasher, tap lines)
- ✔ Inspection of rough-ins completed
Week 2: Cabinet Installation
- ✔ Base & wall cabinets installed
- ✔ Pantry & custom joinery fitted
- ✔ Rangehood ducting installed
- ✔ Accurate measurements for stone benchtops taken
Waiting Period: 10 Business Days
⏳ Stone benchtops are custom-made off-site.
Please allow approximately 10 business days. Delays may occur depending on material availability and fabrication.
After Stone Installation
- ✔ Plumber returns to connect tapware, sink, dishwasher
- ✔ Electrician returns to install appliances & lighting
Final Steps
- ✔ Plasterer finishes patchwork or ceiling repairs
- ✔ Tiler completes splashback and floor tiling (if required)
- ✔ Final quality check & touch-ups
🛠️ Your dream kitchen takes careful coordination — thank you for your patience during the process!