Kitchen Renovation Timeline

Week 1: Preparation & Demolition

  • ✔ Site inspection & layout planning
  • ✔ Demolition of existing kitchen
  • ✔ Removal of cabinetry, appliances & flooring
  • ✔ Structural changes (if required)

End of Week 1: Electrical & Plumbing Rough-In

  • ✔ Electricians install wiring & lighting points
  • ✔ Plumbing rough-in (sink, dishwasher, tap lines)
  • ✔ Inspection of rough-ins completed

Week 2: Cabinet Installation

  • ✔ Base & wall cabinets installed
  • ✔ Pantry & custom joinery fitted
  • ✔ Rangehood ducting installed
  • ✔ Accurate measurements for stone benchtops taken

Waiting Period: 10 Business Days

Stone benchtops are custom-made off-site.
Please allow approximately 10 business days. Delays may occur depending on material availability and fabrication.

After Stone Installation

  • ✔ Plumber returns to connect tapware, sink, dishwasher
  • ✔ Electrician returns to install appliances & lighting

Final Steps

  • ✔ Plasterer finishes patchwork or ceiling repairs
  • ✔ Tiler completes splashback and floor tiling (if required)
  • ✔ Final quality check & touch-ups

🛠️ Your dream kitchen takes careful coordination — thank you for your patience during the process!