Week 1: Demolition & Preparation
- ✔ Site inspection & layout confirmation
- ✔ Demolition of existing fixtures, tiles & fittings
- ✔ Removal of cabinetry, toilet, bath, shower, etc.
- ✔ Initial clean-up & prep of surfaces
Week 1 (End): Plumbing & Electrical Rough-In
- ✔ Plumbing set-out for vanity, toilet, shower, bath
- ✔ Electrical wiring for lighting, fans & power points
- ✔ Compliance inspections if required
Week 2: Structural & Surface Work
- ✔ Wall sheeting, waterproofing & niche construction
- ✔ Floor leveling or screeding (if needed)
- ✔ Drying time for waterproofing membranes
Week 3: Tiling
- ✔ Wall & floor tiles laid
- ✔ Grouting & sealing
- ✔ Feature tiling (if applicable)
- ⚠ Shower screen can only be measured once tiling is complete
- ⏳ Manufacturing of a custom shower screen takes approximately 3 weeks
Week 4: Fit-Off & Finishing
- ✔ Vanity, mirror, and toilet installed
- ✔ Taps, towel rails & accessories fitted
- ✔ Electrical fit-off (lights, fan, switches)
- ✔ Final plumbing connections & testing
Final Checks & Clean-Up
- ✔ Quality control inspection
- ✔ Caulking, silicone, paint touch-ups
- ✔ Site clean & client walk-through
After Completion (Shower Screen Installation)
- ✔ Custom-made shower screen installed ~3 weeks after tiling
- ✔ Final cleaning & sealing of any remaining gaps
🛁 A full bathroom renovation typically takes 4–6 weeks, plus the additional lead time for shower screen manufacturing. We’ll keep you informed at every step!