Bathroom Renovation Timeline

Week 1: Demolition & Preparation

  • ✔ Site inspection & layout confirmation
  • ✔ Demolition of existing fixtures, tiles & fittings
  • ✔ Removal of cabinetry, toilet, bath, shower, etc.
  • ✔ Initial clean-up & prep of surfaces

Week 1 (End): Plumbing & Electrical Rough-In

  • ✔ Plumbing set-out for vanity, toilet, shower, bath
  • ✔ Electrical wiring for lighting, fans & power points
  • ✔ Compliance inspections if required

Week 2: Structural & Surface Work

  • ✔ Wall sheeting, waterproofing & niche construction
  • ✔ Floor leveling or screeding (if needed)
  • ✔ Drying time for waterproofing membranes

Week 3: Tiling

  • ✔ Wall & floor tiles laid
  • ✔ Grouting & sealing
  • ✔ Feature tiling (if applicable)
  • ⚠ Shower screen can only be measured once tiling is complete
  • ⏳ Manufacturing of a custom shower screen takes approximately 3 weeks

Week 4: Fit-Off & Finishing

  • ✔ Vanity, mirror, and toilet installed
  • ✔ Taps, towel rails & accessories fitted
  • ✔ Electrical fit-off (lights, fan, switches)
  • ✔ Final plumbing connections & testing

Final Checks & Clean-Up

  • ✔ Quality control inspection
  • ✔ Caulking, silicone, paint touch-ups
  • ✔ Site clean & client walk-through

After Completion (Shower Screen Installation)

  • ✔ Custom-made shower screen installed ~3 weeks after tiling
  • ✔ Final cleaning & sealing of any remaining gaps

🛁 A full bathroom renovation typically takes 4–6 weeks, plus the additional lead time for shower screen manufacturing. We’ll keep you informed at every step!